| Client |
Drainage Services Department, Hong Kong |
| Contract |
DC/96/17 |
|
Contract amount |
€ 107.440.262,67 |
| Start |
02/1998 |
| Completion |
06/2001 |
| Works performed by |
PAUL Y - SELI Joint Venture made of/composta da: |
| Composed by |
PAUL Y Construction Co. Ltd SELI SpA | | 51% 49% |


|
MAJOR WORKS
|
|
Two tunnels for a total length of 9,5 km : |
-
Tunnel C from Tseung Kwan O to Kwun Tong, 5.3 km long, 4.23 m diameter, which links the shafts previously excavated by another contractor.
|
-
Tunnel A-B from Chai Wan to Kwun Tong via Shau Key Wan, 4.2 km long, 3.2m diameter, which links other two shafts to Kwun Tong shaft previously excavated by another contractor.
|
-
For the excavation of both tunnels, two main beam type TBMs were adopted.
|
-
Both tunnels are located 100 metres beneath the seabed and highly urbanised reclamation areas.
|
|
 |

|
CONSTRUCTION METHODS AND EQUIPMENT
|
|
Tunnel excavation |
|
Technical specification of TBM are: |
|
4,23 m |
|
19" = 482 mm |
|
9.340 kN |
|
12.1 rev/min |
|
1.342 kW |
|
Technical specification of TBM are: |
|
3.2 m |
|
17" = 432 mm |
|
5.600 kN |
|
14.6 rev/min |
|
746 kW |
|
Tunnel lining |
|
Temporary rock supports installed according to the NATM |
|
Fibre reinforced concrete pipe to be built inside the tunnels: two parallel 1.35 m. diameter pipes inside the 4.23 m. diameter tunnel and single variable from 1.20 to 1.35 m. diameter pipe inside the 3.2 diameter tunnel. |
|
|
|

|
GEOLOGY
|
|
Volcanic Tuffs and Granites with UCS ranging from 80 to 350 MPa
|
|

|
 |
|